The scope was to design, supply, install and commission a temporary 40m mast at both Guildford and Keighley. The reason for the temporary mast was because the RF levels of the permanent DAB and FM antennas where too high to allow the work teams to get access to the UHF TV transmit antennas on top of each structure.
SOLUTION
After design approval work began on the temporary structures, installing both DAB and FM antennas at each location. Once the commissioning was complete and the temporary masts working efficiently work could begin on the existing towers. Once the existing towers were rigged up the DAB and FM antennas were isolated and removed. This in turn allowed for the top main UHF TV antennas to be replaced.
In the case of Keighley a helicopter was deployed to replace the TV antenna as there was a blanket ban on large cranes in the area. With works finished on the existing towers we then began the switch over and decommission of the temporary masts.
BENEFIT
By using our temporary solutions at both Guilford and Keighley our customer ensured that no transmission interruptions occurred to the public. Works were completed in around 5 weeks on each site and were on budget and within agreed deadlines.